The critical path on a project can change as the project progresses. select one:

a. true

b. false

Respuesta :

mirrorkitten
mirrorkitten mirrorkitten
  • 02-04-2019

The answer is True.

In project management, critical path refers to a sequence of stages that would require the smallest amount of time possible to bring a project to completion.

Critical path can change during a project since there might be circumstances during it which would lead certain activities to be finished longer or faster. Critical path can be determined by a specialized algorithm technique.

Answer Link

Otras preguntas

There is a positive association between number of drowning and ice cream sales, this association is likely
solve the proportion 3.5/d = 14/15
The Duke of York split New Netherland into which of the following two colonies?
How was the African slave trade adapted to European needs?
How many 2 over 3 foot pieces can Wendy cut from the 5 and 1 over 3 feet of ribbon? Show your work Using the information in Part A, interpret the meaning of the
Line j passes through points (-6,1) and (-3,6) .line m is parallel to line j and passes through point (15,-1). what is the equation of line m ?
what is The temperature was 68°F. Later that day the temperature was 82°F. How much does the temperature need to rise or fall to return to the original tempera
What are the physical properties of the wax in a burning candle
what is a suggested solution to a scientific problem
1/2 over 2 equals to 3 over X