Rick, a homebuilder, uses job order costing for his business. Each new home is a single job. During April, Rick started three new houses, one of which was Job Tudor2. Rick purchased $150,000 of materials for the new home orders and stored them in a warehouse to be brought to the job sites as needed. In April, Rick requisitioned $85,000 of material for Job Tudor2. Direct labor on Tudor2 was $4,800 in April. Overhead is applied at 150% of direct labor cost. What is on the job cost sheet for Tudor2 at April 30?