Six people to can perform a task in 8 days. If we add 2 equally able people, how long would it take?

Respuesta :

madankapoor10
madankapoor10 madankapoor10
  • 24-03-2014
1 man does 1/48th piece of work per day
then 8 man do 1/6th piece of work per day
so they can do the work in 6 days

Answer Link
salmheiri
salmheiri salmheiri
  • 21-02-2022

Answer:

6 days

Step-by-step explanation:

Answer Link

Otras preguntas

what shoul I include in my essay about my favourite film?
how do you solve 4x+5y=20?​
I need help with these problems please help
michalangelos prefferee art form was​
the positive phototropism shown by shoots is caused by the movement of?
The kinetic energy of a rotating body is generally written as K=12Iω2, where I is the moment of inertia. Find the moment of inertia of the particle described in
tacey has a square piece of cloth. She cuts 3 inches off of the length of the square and 3 inches off of the width. The area of ne smaller square is the area of
what is 32 % of 50 ?
Roosevelt came from a prominent family discuss his family and backround
One mole of nitrogen and one mole of neon are combined in a closed container at STP.How big is the container?V = __________ L